Doctor Vent has serviced 3,200+ properties since 2011. These are three of them, with the numbers, the deficiencies we found, and what changed afterwards.
Garden-Style Apartment Community
units
18
buildings
9
days
Read the case study →
Luxury Multifamily Community
units
24
buildings
11
days
Read the case study →
Senior Living Community
units
9
buildings
6
days
Read the case study →
What Every Project Has in Common
Airflow verification at every unit. Before and after photographs of every unit. A deficiency log that names what is broken and where. And a completion certificate referencing NFPA 211 that goes straight into your compliance file.
The deficiencies are why this matters. In every one of these projects, airflow verification surfaced physical duct problems — disconnected transitions, blocked rooftop terminations, restricted upper-floor runs — that cleaning alone would never have revealed and that the property’s own maintenance team had not found.